NWR Driven

Red Water, AB

Contract Value:

$14 million

Prime Consultant:

Flour

Project Owner:

NWR

Contract Format:

Specialist GC – Piling only

Completion Date:

January 2015

Contract Duration:

6 months

Graham was the first contract on site to install permanent works. Due to changeable soil conditions piles were driven deeper that initially anticipated and good planning and scheduling allowed for improved interfacing between other contractors and reduced delays due to late pile design. As well, delays were reduced in pile acceptance and good access for re strikes, over 300 PDA tests, and 5 static load tests.

In total, over 750 splices completed on the piles. This project was completed on schedule with zero quality issues.