Project Categories

View More
Industrial

Keephills 3 Power Project Site Prep

Keephills, AB

Contract Value:

$21 million

Prime Consultant:

Colt Engineering Corporation

Project Owner:

Capital Power

Contract Format:

Lump Sum

Completion Date:

January 2011

Contract Duration:

48 months

The project included the demolition of existing foundations and buildings; mass excavation for the Power Island Foundation; common fill and granular placement required for site grading; site drainage; the construction of access roads and laydown areas; the construction of a storm water pond and a new storm sewer system; site grading for the Coal Handling Facility; and the construction of an ash haul road.