Strathcona County’s Public Yards Expansion and Modernization

June 1, 2021

Graham has been awarded the CDN$23.2 million Strathcona Public Yards project. This project for Strathcona County, a municipality located just east of Edmonton, Alberta, involves three main phases:

  1. Phase 1 will involve construction of the new pre-engineered shop building. Once the pre-engineered shop building is completed, the operations of the service bays in the existing office building will be moved to the new service building.
  2. Phase 2 will involve the expansion of the existing office building on the west end. The expansion will house new locker rooms and training space.
  3. Phase 3 will involve converting the four service bays in the west end of the existing building to office space and adding a 2nd floor of offices over this area. Phase 3 will also begin the modernization of the existing office building – updating and re-organizing the office space and expanding southeast corner of the existing building to accommodate a new main entrance complete with elevator.

The project was qualification-based, with a stipulated price component, and is scheduled to begin immediately.

Other Recent News

Granville Bridge Rehabilitation Advances in Active Urban Corridor

Granville Bridge Rehabilitation Advances in Active Urban Corridor

Project Overview The Granville Bridge south approach ramps rehabilitation project is advancing in downtown Vancouver, with major components complete and remaining work progressing toward completion. Originally constructed in 1954, the Granville Bridge is a key...

Fish Creek Wastewater Treatment Plant Upgrades

Fish Creek Wastewater Treatment Plant Upgrades

Year One Progress Update The Fish Creek Wastewater Treatment Plant Upgrades project in Calgary, Alberta has completed its first year of active construction. Following site mobilization in Fall 2025, preconstruction activities advanced and five work packages have now...