HGST Yerba Buena Tool Relocation
Location: San Jose, CA
The HGST Yerba Buena Tool Relocation involved moving research and development tools, equipment and supporting laboratories from a satellite facility to the company’s main South San Jose campus, now part of Western Digital.

The scope included safe-off, packaging, transport, installation, fit-up and commissioning of specialized tools and equipment. Approximately 25,000 sq. ft. of laboratory and cleanroom space was also constructed across several existing buildings to accommodate the relocated equipment.
The work was completed within an accelerated schedule.

Learn more about Graham’s expertise delivering Advanced Technology facilities – Advanced Technology: Building Data Centers Requires More Than Scale
Contract Value
$25M USD
Prime Consultant
DGA
Project Owner
Western Digital Inc.
Contract Format
CM-at-Risk
Completion Date
February 2017
Contract Duration
17 months